KRL | Custom Lithium Battery & Energy Storage(BESS)Manufacturer

Download Technical Specs PDF

Contents

Egypt Industrial Factory 2MW/4MWh PV + Battery Storage + Diesel Microgrid Solution for a 4MW Load

egypt-industrial-krl-2mwh-ess-factory1

Egypt industrial battery storage system projects should never be sized from MW alone. A factory buyer in Alexandria approached KRL Power asking for a 2MW industrial battery system. After technical clarification, the real requirement became clear: approximately 4MW of available grid power, an existing 500kW solar PV system, planned PV expansion toward 2MWp within six months, and at least eight hours of backup for the buyer's own factory.

This is exactly the type of project where simply quoting a 2MW battery can create an expensive sizing error. MW defines how much instantaneous power the PCS can deliver; MWh determines how long the battery can support the required load. KRL Power therefore recommends starting from the customer's critical-load profile, outage duration, PV architecture and diesel strategy before finalizing the commercial quotation.

Based on the information currently available, the recommended Phase 1 platform is two KRL 1MW/2MWh all-in-one ESS units connected in parallel through an AC combiner/PCC cabinet, providing 2MW combined PCS power and 4MWh nominal battery energy. The same platform can support PV self-consumption, peak shaving, fast backup, generator-assisted long-duration operation and future expansion.

Egypt Factory Project Requirements and the Real Sizing Question

The customer's initial request is commercially attractive, but the decisive engineering input is still missing: how many kilowatts of critical factory load must remain online for the full eight-hour outage window? A factory may have a 4MW grid connection while only 300kW, 800kW or 1.5MW of production and safety loads actually need backup.

Project itemCustomer requirementEngineering implication
LocationAlexandria, EgyptOutdoor thermal, dust, corrosion and grid conditions must be considered
ApplicationIndustrial factoryCritical and non-critical loads should be separated
Available grid powerApprox. 4MWGrid connection capacity does not equal required backup load
Existing solar PVApprox. 500kWExisting AC/DC topology and inverter data must be checked
PV expansionToward 2MWp within 6 monthsPV architecture should be reserved in the Phase 1 design
Requested ESS power2MWTwo 1MW PCS units can provide the requested storage power
Backup targetAt least 8 hoursRequired MWh depends on the actual critical-load kW
Recommended Phase 12 × KRL 1MW/2MWh ESS2MW / 4MWh modular platform with AC-side parallel connection
Diesel generatorBackup sourceExtends autonomy during prolonged grid outages

Why 2MW Does Not Mean Eight Hours of Backup

The proposed system contains two 1MW/2MWh units. Combined PCS power is 2MW and nominal battery energy is 4MWh. If the project uses an 80% operating depth of discharge for preliminary analysis, nominal usable battery-side energy is approximately 4MWh × 80% = 3.2MWh before PCS losses, cooling consumption, auxiliary loads and minimum SOC reserve.

Critical loadSimplified theoretical runtime from 3.2MWhWhat the buyer should understand
300kW≈10.7 hoursPotentially compatible with an 8-hour target after detailed loss and reserve analysis
350kW≈9.1 hoursA realistic range to examine for conservative 8-hour backup sizing
400kW≈8 hoursTheoretical only; real design should allow conversion and auxiliary losses
800kW≈4 hours4MWh is not an 8-hour battery-only solution at this load
1MW≈3.2 hoursDiesel support or additional MWh is required for long outages
2MW≈1.6 hoursMaximum combined PCS-class backup power has short battery-only duration
4MWNot possible from ESS aloneThe two PCS units provide 2MW combined output, so the full 4MW plant cannot be battery-backed directly

If the customer requires 2MW continuously for eight hours, the load alone needs about 16MWh of usable energy. At an 80% DoD assumption, that is roughly 20MWh nominal before additional engineering margin. A full 4MW factory load for eight hours represents about 32MWh of load energy before losses. This is why KRL should size the project around the critical backup load, not around the site's 4MW grid connection.

Recommended Phase 1: 2 × KRL 1MW/2MWh All-in-One ESS in Parallel

For the currently known requirements, a practical first stage is two KRL 1MW/2MWh all-in-one energy storage systems operating as independent power blocks and paralleled on the AC side through a dedicated PCC/main switchgear cabinet. This gives the factory 2MW of combined PCS capability and 4MWh of nominal battery energy without treating the installation as one inseparable battery block.

KRL system parameterPer unitTwo-unit project value
Battery energy2MWh LiFePO44MWh nominal
PCS rated power1MW2MW combined
PV maximum inputUp to 960kWUp to 1.92MW published combined direct PV input
MPPT8 channels16 MPPT channels total
Grid operationOn-grid / off-gridParallel industrial microgrid platform
Switching<10msFast transition capability subject to complete site protection design
Diesel interfaceGEN AC interfaceGenerator-assisted long-duration microgrid
CoolingLiquid coolingSuitable for demanding C&I thermal management
Battery enclosureIP65Outdoor deployment subject to site engineering
CommunicationRS485 / WiFi / 4GLocal and remote monitoring

For buyers comparing industrial ESS vendors, the advantage is not simply the 4MWh number. The KRL architecture combines battery, PCS, BMS, MPPT, EMS and generator integration in a modular platform, reducing field integration complexity and leaving a clear path for PV and storage expansion.

The Planned 2MWp Solar Expansion Needs One Important Check

The customer plans to expand solar toward 2MWp. The current 2MWh KRL configuration provides up to 960kW of PV input per unit, so two standard units provide approximately 1.92MW of published direct PV-input capability. The final design should therefore not promise that an exact 2MWp array will all connect directly to the integrated MPPTs without verification.

Because the site already has 500kW of solar PV, KRL should first obtain the existing inverter model and single-line diagram. A functioning AC-coupled PV plant should not be unnecessarily rebuilt just because the new ESS contains MPPT.

Correct Electrical Topology for the 2MW/4MWh Hybrid Microgrid

egypt-2mw-4mwh-pv-storage-diesel-microgrid-topology1

The electrical architecture should clearly show two independent ESS units rather than one artificial 4MWh container. Each storage unit has its own battery, PCS, BMS, MPPT and unit controller. Their PCS AC outputs connect through separate breakers to the common PCC/main AC switchgear.

Why the Grid Connects to the PCC, Not Directly to One ESS

The utility grid, factory loads and both ESS branches meet at the PCC/main switchgear. This is the correct location for common metering, protection, grid isolation, synchronization, breaker control and import/export management. The two batteries should not be chained together on the DC side, and the grid should not bypass the PCC to feed only one storage unit.

Why the Diesel Generator Uses Protected GEN Feeders

The diesel generator is a long-duration backup source, but it should not be shown as an uncontrolled cable connected into two storage units. The generator passes through a distribution/protection section and then to the approved GEN AC interfaces. Final breaker ratings, synchronization logic, generator controller protocol and multi-ESS generator coordination must be confirmed during project engineering.

How the Egypt Factory Microgrid Operates in Normal and Outage Conditions

Daytime: Use Solar First and Store Excess Energy

During normal daytime operation, solar generation should serve factory loads according to the agreed control strategy. Available excess PV can charge the batteries, increasing solar self-consumption and reducing the amount of electricity imported from the utility. The EMS should keep enough SOC reserve for the customer's backup requirement rather than simply maximizing daily battery cycling.

Peak Demand: Use Both PCS Units to Limit Grid Import

If factory demand reaches 3.5MW while the operator wants to limit utility import to 2MW, the two ESS units can theoretically supply the remaining 1.5MW within their 2MW combined PCS capability. The financial benefit depends on the customer's real tariff, maximum-demand charging method and operating schedule, so KRL should model savings from interval data instead of promising a generic percentage.

Grid Failure: Isolate the Utility and Keep Critical Loads Running

When the grid fails, the PCC protection system must isolate the internal microgrid from the failed utility. The ESS then supports the approved critical-load bus according to the commissioned off-grid/grid-forming strategy. The customer should not interpret a 4MW plant rating as a promise that the 2MW PCS platform can carry the entire factory during an outage.

alexandria-industrial-factory-night-backup1

Long Outage: Battery and Diesel Work Together

For an eight-hour or longer outage, diesel support can dramatically reduce the amount of battery energy that must be purchased purely for rare long-duration events. The ESS handles fast transfer, PV shifting, power smoothing, generator start bridging and short-duration high-power support. The generator then supplies part of the prolonged load and can support battery SOC when solar generation is insufficient.

egypt-krl-ess-diesel-generator-backup1

How to Meet the Customer's Eight-Hour Backup Target

Option A: Keep 2MW/4MWh and Back Up Only Essential Loads

If the verified eight-hour critical load is in the 300–350kW range, the 4MWh platform may be close to an appropriate battery-only solution after system losses, reserve SOC, ageing and thermal conditions are incorporated. This can be the lowest-CAPEX path when only selected production and safety loads need continuity.

Option B: Use 2MW/4MWh ESS Plus Diesel for Long-Duration Backup

For many factories, this is the stronger commercial solution. The battery provides immediate continuity and daily energy-management value, while the generator covers extended outages. The customer avoids purchasing very large MWh capacity solely for occasional long blackouts while still gaining PV utilization, peak shaving and fast backup from the ESS.

Option C: Expand Battery Capacity for Battery-Only Eight-Hour Operation

If the customer requires eight hours without generator contribution, battery energy must be increased according to the verified critical-load kW. For example, 2MW of critical load for eight hours requires about 16MWh usable energy. At 80% DoD, nominal battery energy is already about 20MWh before conversion losses, auxiliaries, ageing and design reserve.

Backup strategyBest fitMain commercial trade-off
2MW/4MWh battery-only for selected loadsCritical load roughly compatible with the available energyLowest first-stage battery CAPEX but requires strict load prioritization
2MW/4MWh ESS + dieselLong outages where generator use is acceptableStrong balance of daily savings, fast backup and long-duration resilience
Larger battery-only systemCustomer requires long autonomy without dieselHigher CAPEX and larger footprint but lower generator dependence

Egypt Site Engineering, Expansion Plan and Final RFQ Inputs

Why Liquid Cooling Matters in Egypt

Large industrial battery systems must keep cell temperatures consistent. KRL's 2MWh platform uses liquid-cooled battery thermal management. For an Alexandria installation, detailed design should also consider summer ambient temperature, direct solar exposure, dust, cable derating, drainage, service clearances and possible salt-air corrosion near the Mediterranean coast.

What KRL Needs Before Issuing the Final Technical and Commercial Proposal

The current information is sufficient to recommend the 2MW/4MWh platform as a Phase 1 direction, but not sufficient to guarantee eight-hour autonomy or release a final manufacturing BOM. KRL should request the following items in one technical clarification package.

RFQ inputWhat the customer should provideWhy it matters
Factory SLDUtility, transformer, PV, generator, bus and load connectionsConfirms the real electrical architecture
Interval load data15-minute or 30-minute load profileDetermines peak-shaving value and actual ESS dispatch
Critical-load listkW/kVA of loads that must survive outagesDetermines required PCS power and MWh
Existing PV500kW inverter model and AC/DC topologyDetermines how existing solar should be retained or integrated
Future PVTarget modules, strings and inverter/MPPT planConfirms the practical path toward 2MWp
GeneratorRated kW/kVA, voltage, frequency and controller interfaceConfirms long-duration backup integration
Grid/PCCVoltage level, transformer capacity and import/export rulesDetermines switchgear, protection and charging limits
Site layoutAvailable area, cable routes and installation photosConfirms civil work, spacing and cable design
Commercial scopeEXW/FOB/CIF preference and Alexandria delivery requirementsMakes quotations technically and commercially comparable

For related backup design principles, KRL buyers can also review the battery backup for power outages engineering guide.

Engineering Recommendation: Build the Microgrid Around the Critical Load, Not the 4MW Nameplate

For this Alexandria factory, 2 × KRL 1MW/2MWh all-in-one ESS units form a technically logical first-stage platform. The project receives 2MW of combined PCS power, 4MWh of nominal battery energy, modular AC-side parallel operation, direct PV-input capability, fast backup functionality and a generator-assisted path for prolonged outages.

The system is well suited to peak shaving, increased PV self-consumption, backup of correctly selected critical loads and staged microgrid expansion. But KRL should not present 4MWh as an automatic eight-hour backup solution for the entire 4MW plant. The decisive number is the verified critical-load kW during an outage.

Once the factory provides its SLD, interval load data, critical-load schedule, PV configuration and generator information, KRL can determine whether the best investment is 2MW/4MWh, a larger-MWh battery platform, or a 2MW/4MWh ESS + diesel hybrid strategy. That is the difference between selling a battery and engineering a factory energy solution.

Why KRL Power Is a Strong Fit for This Project

KRL Power focuses on commercial and industrial energy storage integration. The company's approach combines long-life battery cells, liquid cooling, intelligent BMS, PCS, EMS, multi-layer protection and modular all-in-one architecture. For an international factory project, that integration is valuable because the customer needs one coordinated power system rather than separate equipment that must be engineered together after delivery.

FAQ

No, not if the full factory continuously consumes 4MW. A 4MW load running for eight hours requires about 32MWh of load energy before losses, while the two recommended PCS units provide 2MW combined output. The project must be sized from the critical backup load rather than the site's maximum grid connection.

At an 80% preliminary DoD assumption, 4MWh nominal battery energy gives about 3.2MWh of battery-side usable energy before system losses. The theoretical eight-hour average is 400kW, but a real design should be lower because PCS losses, auxiliaries, reserve SOC, ageing and site conditions must be included.

Two independent 1MW/2MWh units provide 2MW/4MWh combined capacity while supporting AC-side parallel operation, unit-level protection, modular maintenance, coordinated power sharing, staged PV integration and future expansion.

Potentially yes. KRL should first review the existing PV inverter model and single-line diagram. If the existing 500kW system is already AC-coupled and operating correctly, it may be more practical to retain it and integrate the new storage system at the site AC bus rather than rebuilding working PV equipment.

The current 2MWh KRL configuration provides up to 960kW PV input per unit, or about 1.92MW published combined direct PV-input capability for two units. The final 2MWp design therefore requires confirmation of array sizing, permitted DC oversizing or a hybrid AC/DC PV architecture.

Yes. The current project configuration uses a 1MW PCS per 2MWh unit. Two correctly paralleled units therefore provide approximately 2MW combined PCS capability.

The PCC is the common AC coupling point for ESS #1, ESS #2, the utility grid and factory loads. It also provides the correct location for branch breakers, metering, protection, grid isolation, synchronization and import/export control.

The proposed architecture routes the generator through generator distribution and protection before the approved GEN AC interfaces. The Master EMS coordinates generator start/stop, battery SOC, factory load and operating mode. Final generator breaker sizing, controller protocol and multi-unit synchronization must be confirmed during project engineering.

Not from the battery system alone because the two PCS units provide 2MW combined output. The plant should separate critical and non-critical loads. If the customer wants more than 2MW of islanded power or eight-hour operation, generator contribution and/or additional ESS power and energy must be engineered.

The current product direction uses liquid-cooled battery thermal management and an IP65 battery enclosure. Final site design should still verify maximum ambient temperature, direct sun, dust, coastal corrosion exposure, drainage, cable derating, maintenance clearance and fire access.

Yes. Modular scalability is one of the main reasons to use independent 2MWh blocks. Additional ESS units can be evaluated later according to the factory's verified backup requirement, load growth, PV expansion and PCC capacity.

Send the factory SLD, 15- or 30-minute load profile, critical-load list, existing PV inverter data, future PV plan, generator specifications, grid/PCC voltage, transformer rating, import/export requirements, installation layout, delivery destination and required backup duration.

Get Your Custom Energy Solution in 24 Hours

Stop Paying for Brand Markups. Partner Direct with a 20-Year Source Factory.

KRL Power — Source Factory Behind Global Energy Projects

Trusted Worldwide:

UL, CE, IEC, UN38.3

Hot Models:

B65 · B100 · B241 · B26LL · B61LL · B522L · B2M6L

Applications:

Factories · Solar Farms · Mining · Islands · Data Centers

Tell us your project — we'll design the system for you.