KRL | Pasgemaakte litium-battery- en energiestoorfabrikant (BESS)

Laai die PDF met tegniese spesifikasies af.

Contents

Two 125 kW Cabinets and the 250 kW Class

One feeder inside 125 kW and 189 A after motors start: buy one KRL-B261L 125 kW / 261 kWh.

One feeder that already overlaps at 140-180 kW, or needs 375 A and 522 kWh in one object: buy one KRL-B522L 250 kW / 522 kWh.

Two feeders that grow on different dates, each still inside 125 kW: buy two B261L cabinets.

261 + 261 does print 250 kW and 522 kWh. That is the energy line. Current, PV ports and the pad stay on separate rows. I still price the pair and the single 250 kW cabinet as different machines. The rest of this page is the sheet that shows why.

Official KRL-B261L 125 kW 189 A cabinet beside KRL-B522L 250 kW 375 A cabinet
Quote lineWhat lands on site
One 375 A converterTwo 189 A converters
One 240 kW PV inputTwo 120 kW PV inputs
One 4900 kg padTwo 2600 kg pads
One diesel handshakeTwo cabinets that both list a diesel port
One EMS objectTwo boxes sharing one feeder plan

KRL Krag keeps both classes on the outdoor list for that reason. The second box has its own ports, its own current limit and its own crane note.

What the two sheets print

I copy these rows into the comparison file and stop there. Empty cells on a live product page stay empty. I do not fill them from the other cabinet.

ItemB261LTwo B261LB522L
ModelKRL-B261L-125H3S-120M1-HX1two of that stringKRL-B522L-250H3S-240M2-HX1
Power125 kW on-grid and off-grid125 kW + 125 kW250 kW on-grid and off-grid
Energy261 kWh522 kWh522 kWh
Max AC current189 A189 A per cabinet375 A
Voltage / frequency400 Vac / 230 Vac, 50/60 Hzsame400 Vac / 230 Vac, 50/60 Hz
Battery832 V, 314 Ah, LiFePO4two packs832 V, 628 Ah, LiFePO4
Max PV120 kW120 kW + 120 kW240 kW
MPPT1 or 4 channels, 200 Atwo separate inputs2 channels, 200 A + 200 A
Max PV voltage950 Vdcsame950 Vdc
MPPT window250-850 Vdcsame250-850 Vdc
Parallel limit10already two of ten6
Diesel portYesYes on eachYes
Switchingunder 10 msunder 10 ms eachunder 10 ms
CommunicationRS485 / WiFitwo nodesRS485 / WiFi
Battery IPIP65IP65 eachIP65
Size980 x 1300 x 2320 mmtwo footprints2480 x 1400 x 2050 mm
Massabout 2600 kgabout 5200 kg on two liftsabout 4900 kg
Coolingbattery liquid, PCS intelligentsame on eachbattery liquid, PCS intelligent
Window-10 C to 55 C, 5-95%, under 2000 msame-10 C to 55 C, 5-95%, under 2000 m

Energy matches. Wiring and steel do not.

261 / 125 is about 2.1 hours. 522 / 250 is about 2.1 hours. That is nameplate energy divided by nameplate power. Usable time is shorter. Four cuts come off before anyone should promise hours: the SOC window in the contract, DC to AC conversion, auxiliary load on the cabinet, and the reserve the operator refuses to empty. KRL does not publish one usable-energy percentage for every site. Hours belong in the configuration, measured at the agreed meter point.

If the feeder already needs 250 kW, the project language sits on the 522 kWh / 250 kW solar-storage-diesel cabinet page. This page is for the buyer still stacking two 125 kW boxes to avoid that drawing.

Shared lines that do not pick the class: LiFePO4, 832 V, liquid battery cooling, intelligent PCS cooling, fire protection listed Yes, IP65 on the battery, under 10 ms switching, diesel port Yes, RS485 / WiFi, -10 C to 55 C, 5-95% humidity, altitude under 2000 m. I leave those on both product pages. 125 kW or 250 kW still does the picking. So does 189 A or 375 A.

How the site usually presents itself

One feeder, 80-110 kW running, motors staggered. I keep one B261L on the table. Finish the start review before anyone locks 125 kW. A quiet Tuesday logger leaves the first ten seconds after an outage unproven. Night load on that same feeder can look even quieter. The class still follows the worst overlap, not the lunch-time average.

One feeder, 140-180 kW when two lines and a compressor overlap. I open B522L. Two B261L cabinets can print 250 kW and still hand the bus two 189 A converters. The plant asked for one 250 kW object. At 400 Vac three-phase, 125 kW near unity power factor sits around 180 A. The published ceiling is 189 A. 250 kW sits around 361 A. The published ceiling is 375 A. A 160 kW overlap already belongs on the 250 kW row before anyone talks about 522 kWh.

Two feeders that grow on different dates. Two B261L cabinets can be the honest buy. Feeder A stays on cabinet A. Feeder B stays on cabinet B. B261L still has room up to 10 if a third feeder appears later. The purchase order should keep the pair named as two B261L cabinets. The day someone ties those two AC outputs onto one process bus, the job has changed. That drawing needs a parallel study, protection settings and an EMS object that treats two converters as one feeder. I price that work before I call the pair a bargain.

The rest of the outdoor map lives in the commercial and industrial energy storage system selection guide. I only settle the 125-plus-125 shortcut here.

Official KRL-B261L versus KRL-B522L class decision: 189 A or 375 A

Current splits the quote first

189 A is the B261L ceiling. 375 A is the B522L ceiling.

Adding energy labels leaves each B261L on its own 189 A. If those two converters share one bus, EMS and protection have to coordinate them. B522L puts 375 A on one published converter.

I write the start package against that number.

The start math belongs with the motor-start page. This page keeps the current column honest. A 90 kW running log can still hide a 40 kW motor that closes with the dryer. That event lives on the current row. It does not live on the 261 kWh row.

Charging yards hit the same wall for another reason. Two DC chargers plus house load can sit above 125 kW while daily energy still looks modest. I size power before I size hours. A fuel-station layout that already lives at 250 kW is on the 250 kW / 522 kWh fuel-station energy storage page.

On-grid rated power and off-grid rated power are both 125 kW on B261L and both 250 kW on B522L. I do not treat the off-grid column as spare headroom. The sheet already printed the same kilowatt number on both sides.

Two ways to park two B261L cabinets

Keep them on two feeders. Cabinet A never sees feeder B. Each 189 A limit stays local. Each 120 kW PV port stays local. Each diesel port can follow its own feeder rule, or both can point at one generator if the start owner is written down. This is the drawing I accept when the plant grows as two processes.

Tie them to one process bus. The energy adds. The current limits stay two. Someone has to decide which cabinet takes the first motor, which cabinet takes the second, and what happens if one cabinet hits 189 A while the other still has room. Parallel number 10 on B261L allows that architecture. It does not erase the extra protection settings, the extra RS485 / WiFi node, or the extra spare-parts line. B522L avoids that conversation by putting 375 A on one converter.

I ask for the single-line before I accept either story. A verbal "we will parallel them later" is not a single-line.

PV ports stay where the sheet put them

B261L lists 120 kW PV, 950 Vdc max, 250-850 Vdc MPPT, 200 A, 1 or 4 channels.

B522L lists 240 kW PV, the same voltage window, 200 A + 200 A, 2 channels.

Two B261L cabinets reach 240 kW if both PV inputs are used and the roof is split. A single string plan into one cabinet still faces a 120 kW port.

Price the extra combiner, the extra trench and the extra MPPT map before anyone calls two cabinets cheaper. A roof already drawn as one 240 kW array wants the B522L port count. A roof that will be built in two phases can live on two 120 kW ports. Write the phase date next to the kW.

Diesel is listed Yes on both sheets. Two ports still need one start rule. Who closes the generator on nights: EMS, PLC, or a person. Write the name. Under 10 ms is the published changeover on both cabinets. A diesel set still needs seconds. In those seconds the signed load rides on the battery or it drops. Two cabinets do not shorten the generator start. They only add a second port that must obey the same rule.

Pads and cranes after the quote

BuyFootprintMassCivil pack
One B261L980 x 1300 mmabout 2600 kgone outdoor pad, one lift
Two B261Ltwo of thoseabout 5200 kgtwo pads, two lifts, two cable sets
One B522L2480 x 1400 mmabout 4900 kgone wider pad, one heavier lift

B261L is the narrow cabinet: 980 mm wide, 2320 mm high. B522L is the wide cabinet: 2480 mm wide, 2050 mm high. A door that accepted the 980 mm box may reject the 2480 mm box. A pad poured 1.0 m wide will not take a 2.48 m footprint. Walk the route from the truck to the pad before the salesman leaves.

Two small cabinets can look easier to walk onto a tight yard. They can also book two crane visits. One 4900 kg cabinet is one visit and one set of anchors. Two 2600 kg lifts add up to about 5200 kg of steel plus a second set of AC cables, DC cables if PV is split, and earths.

A pad poured for 2.6 t will not hold 4.9 t. That invoice arrives after the salesman has left.

If the hall already sits at several hundred kilowatts, I stop stacking yard cabinets. Open KRL-B2M6L 1-2 MW / 2-6 MWh and name the exact model string: KRL-B1M5L-750H3S-720M6-HX1 or KRL-B2ML-1MH3S-960M8-HX1. B261L parallels to 10. B522L parallels to 6. Those limits stay inside the yard class. A 15 t or 19.5 t plant package is a different drawing.

Where the wrong class shows up

Lock 125 kW on a feeder that overlaps at 160 kW. The cabinet still has energy. The converter drops on the start. The line stops. Night-shift plants have already walked that sequence on the 2 a.m. factory blackout recovery page.

Buy two B261L cabinets and draw one 250 kW bus. You now own two current limits, two PV maps and two protection settings. The purchase order said 522 kWh. The electrician inherited two machines. Firmware updates arrive as two nodes. A fault on cabinet A can leave cabinet B holding a feeder it was never sized to hold alone.

Jump to B522L on a 90 kW feeder with no overlap. You paid for 250 kW and 4900 kg on a site that still fits 125 kW and 2600 kg. The extra steel does not calm the process. It does fill a pad that a second process might have used later.

Call two B261L a B522L in the tender. Spare parts, firmware, PV strings and the diesel handshake follow the wrong drawing. The storeman orders a 628 Ah pack language against a 314 Ah cabinet. The PV crew pulls 200 A + 200 A onto a port that lists 200 A.

Leave altitude off the inquiry and then park the cabinet above 2000 m. Both sheets cap altitude under 2000 m. Higher than that, ask for derating in writing. I do not invent the derating factor here.

What I ask for in the meeting

Name one protected feeder. If the meeting keeps adding halls, class is still open.

Write running kW, kVA and power factor from a logger that includes a bad day. Add each large motor, its kW and DOL / soft / VFD. Add which motors close in the same two seconds. Add the first ten seconds after the grid dies. Add PV target, 120 kW or 240 kW, and whether the roof arrives in one phase or two. Add diesel kept or removed, and the name of the start owner.

Then put that pack next to 189 A and 375 A.

I stay on one B261L when the pack stays inside 125 kW / 189 A and 261 kWh after reserve.

I open one B522L when one feeder needs 250 kW / 375 A, or 522 kWh in one object with one 240 kW PV map.

I buy two B261L cabinets when two feeders grow on two dates.

The outdoor list sits under KRL C&I energy storage systems. Drawing order before class is locked sits in how to design a commercial energy storage system.

Send the single-line, the motor list and the first-ten-second sheet. Class falls out of those three files.

Table you can paste into the inquiry

Site factClass that fitsCost if the class is wrong
80-110 kW running, staggered startsone B261Lextra 250 kW steel
140-180 kW overlap on one feederone B522L189 A trips while 261 kWh is still full
Two feeders, two datestwo B261Lone 4900 kg pad on the wrong yard
Two B261L tied onto one process busparallel study firsttwo 189 A limits on a feeder that wanted 375 A
Roof already planned at 240 kW into one cabinetB522L120 kW port rejects the extra string
Roof built in two phases at 120 kW eachtwo B261L or one B522Ldecide before the first trench
Hall already at 400 kW and upB2M6L model stringyard cabinets and plant current on the same drawing

Questions I put on the vendor call

Which object holds 375 A: one converter, or two 189 A boxes?

How is PV landed: one 240 kW map, or two 120 kW maps?

Who owns the diesel start if two cabinets both list a port?

What pad and crane note sits next to 2600 kg and 4900 kg? Does the 980 mm cabinet fit the door that the 2480 mm cabinet will not?

If a third feeder appears, does the site still sit inside parallel 10 or parallel 6?

Which meter point will prove usable hours after the SOC window, conversion and reserve?

Ask those before the price column. Price follows class.

Send feeder single-line, motor list and PV target before locking 125 kW or 250 kW class

V&A

They match on 250 kW and 522 kWh. They split on current (189 A each versus 375 A), PV ports (120 kW each versus 240 kW), mass and pad count.
When the protected feeder stays inside 125 kW after the start review and the signed outage still fits 261 kWh after reserve.
When one feeder needs 250 kW at once, 189 A is already short, or 522 kWh must sit in one cabinet with one 240 kW PV map.
When two feeders grow on different dates and each feeder still fits 125 kW / 189 A.
Motors and chargers trip converters. Energy labels do not start machines. At 400 Vac, 125 kW sits near 180 A and 250 kW sits near 361 A. The published ceilings are 189 A and 375 A.
They can if the roof is split and both 120 kW ports are used. A single string plan into one 120 kW port will not take 240 kW.
Yes. Two ports still need one start owner: EMS, PLC, or a named person. Under 10 ms is the changeover. The generator still needs seconds.
About 2600 kg on 980 x 1300 mm versus about 4900 kg on 2480 x 1400 mm. Two B261L cabinets need two pads and two lifts.
B261L publishes 10. B522L publishes 6. Those limits stay inside the yard class. Parallel on one process bus still needs a protection and EMS plan.
Single-line of the protected feeder, motor list with start method, first-ten-second restart sheet plus PV kW and diesel owner.
A 250 kW cabinet is the class for one feeder that already overlaps near 140-180 kW, needs 375 A, or wants 522 kWh and 240 kW PV in one object. KRL publishes that class as KRL-B522L.
Energy can match at 522 kWh. The site still receives two 189 A converters, two 120 kW PV ports and two pads instead of one 375 A converter, one 240 kW PV port and one 4900 kg pad.
Compare KRL-B261L-125H3S-120M1-HX1 and KRL-B522L-250H3S-240M2-HX1 against the protected feeder current, PV map and pad access before adding a third vendor class.
KRL-B261L-125H3S-120M1-HX1. 125 kW on-grid and off-grid, 261 kWh, 189 A, 120 kW PV, parallel 10, about 2600 kg, 980 x 1300 x 2320 mm.
KRL-B522L-250H3S-240M2-HX1. 250 kW on-grid and off-grid, 522 kWh, 375 A, 240 kW PV, parallel 6, about 4900 kg, 2480 x 1400 x 2050 mm.
Under 10 ms. That is the changeover path. Restart is still a motor list. Both sheets also list battery liquid cooling, PCS intelligent cooling, IP65 on the battery and a diesel port.

Stuur vandag jou navraag

Kry jou pasgemaakte energielosingsplan binne 24 uur

Hou op om te betaal vir handelsmerkopslag. Werk direk saam met 'n bronfabriek met 20 jaar ondervinding.

KRL Power — Bronfabriek agter wêreldwye energieprojekte

Wêreldwyd Vertrou:

UL, CE, IEC, UN38.3

Goeie modelle:

B65 · B100 · B241 · B26LL · B61LL · B522L · B2M6L

Toepassings:

Fabrieke · Sonstrengte · Mynbou · Eilande · Datacenters

Vertel ons van jou projek — ons sal die stelsel vir jou ontwerp.