KRL | Fabricant de batteries au lithium et de systèmes de stockage d'énergie (BESS) sur mesure

Télécharger le PDF des caractéristiques techniques

Contents

Industrial Battery Storage Nigeria: 500 kW Welding Plant

A Nigerian welding plant with a measured 500 kW aggregate load and three 150–200 kW production groups needs enough inverter power to carry scheduled production, absorb operating variation and keep the three-phase bus stable. KRL Power’s published B2M6L 1.5 MWh / 750 kW configuration is a credible starting point for this requirement because its rated power sits 250 kW above the stated aggregate load and its nominal energy equals three hours at a constant 500 kW.

KRL B2M6L 1.5 MWh 750 kW container BESS in a dedicated electrical yard beside a Nigerian 500 kW welding factory

Those two ratios support preliminary selection. Purchase approval still depends on the welders’ input kVA, power factor, current waveform, duty cycle, simultaneous-operation pattern and the proposed 380 V connection. The public B2M6L table lists 400/230 Vac, so the final electrical design must close the 380 V/400 V interface before an order is released.

Six project checks carry the greatest shutdown and contract risk:

Decision itemCustomer requirementPublished KRL referenceProcurement conclusion
Aggregate production load500 kW750 kW on-grid and off-grid rated power250 kW nameplate headroom is available at the published rating
Production groupsThree groups at 150–200 kW1,130 A maximum AC current for the 1.5 MWh configurationVerify group overlap, kVA and transient current
Required bus380 V three-phase400/230 Vac, L1/L2/L3/N/PEDefine transformer, tap setting or approved voltage operating range
Storage target1,500 kWh1.5 MWh nominal energyThree hours is the nominal-energy arithmetic at 500 kW
InstallationOutdoor industrial siteBattery IP65; liquid cooling; fire-protection system listedConfirm enclosure-wide protection and site fire design
Warranty requestFive-year battery warrantyModel-specific warranty terms are not stated publiclyAttach signed warranty schedule to the contract

Buyers can compare the public product range on KRL Power’s commercial and industrial energy storage system page and review the selected B2M6L 1.5 MWh and 2 MWh configurations.

Convert the 500 kW Figure into an Operating Schedule

The 500 kW total describes a system boundary. It does not reveal how the factory reaches that value. Three production groups rated between 150 kW and 200 kW can create several operating states:

Active production groupsPossible connected loadWhat the controls must establish
One150–200 kWMinimum stable operating mode and auxiliary load
Two300–400 kWNormal production overlap and available charging power
Three450–600 kWMaximum permitted overlap, short-duration peaks and load shedding priority

The EMS should receive a simple production priority table. A practical schedule identifies:

This schedule prevents a 500 kW average from being mistaken for a 500 kW maximum. It also gives the factory a clear rule for operating within the BESS power boundary.

Separate the welding-power bus from sensitive control loads in the single-line diagram. PLCs, safety relays, network switches, contactor coils and welder controllers need documented ride-through capability. KRL publishes a switching time below 10 ms for the B2M6L, and the commissioning plan should verify that each critical control remains stable through the actual transition. A dedicated UPS or DC control supply may be required for devices with a shorter ride-through tolerance.

Record Welding Loads in kVA, kW and Current

Welding equipment is frequently specified in input kVA, output current and duty cycle. A BESS proposal based only on the welders’ output rating can miss the electrical input demand. The load register should record the following fields for every major machine:

At 380 V three-phase, 500 kW corresponds to approximately 760 A at power factor 1.0. At power factor 0.85, the current rises to approximately 894 A. These are calculation examples based on the standard three-phase relationship:

Current = Active power ÷ (√3 × line voltage × power factor)

KRL publishes 1,130 A maximum AC current for the 1.5 MWh B2M6L configuration. The current comparison remains preliminary because the published system voltage is 400/230 Vac and the actual welders may produce distorted current. The approved design should use measured RMS current, power factor and harmonic data from representative production cycles.

Map Every Welder to Its Connected Phases

The load register must identify how each welder is connected. A factory described as “three-phase” can still contain large single-phase or line-to-line welders connected to L1–N, L2–N, L3–N, L1–L2, L2–L3 or L3–L1. Total kW can remain below the PCS rating while one inverter leg reaches its current limit.

Record these values for every major welder and production state:

The PCS approval package should state:

A requirement such as “100% unbalanced load” is usable only when the contract defines the phase currents, duration, neutral arrangement and acceptance limits. If the offered PCS cannot support the measured phase concentration, the design must redistribute welders among phase pairs, separate selected loads, add a manufacturer-approved balancing solution or change the PCS architecture. The FAT and SAT should reproduce the approved worst-case phase combination.

Use the Published B2M6L Boundary Correctly

KRL’s public table supports the following 1.5 MWh configuration:

Published itemKRL B2M6L 1.5 MWh configuration
ModelKRL-B1M5L-750H3S-720M6-HX1
Battery chemistryLiFePO4
Rated energy1.5 MWh
Nominal voltage / capacity832 V / 1,884 Ah
On-grid rated power750 kW
Off-grid rated power750 kW
AC voltage400/230 Vac, L1/L2/L3/N/PE
Rated frequency50/60 Hz
Maximum AC current1,130 A
Switching time<10 ms
Maximum PV power720 kW
MPPT channelsSix
MPPT voltage range250–850 Vdc
Maximum PV voltage950 Vdc
PV input current200 A × 6
CommunicationRS485 / WiFi
CoolingLiquid cooling for the battery; intelligent cooling for the PCS
Environmental range−10°C to 55°C; 5–95% RH; below 2,000 m
Size / approximate weight6,058 × 2,438 × 2,896 mm / 15,000 kg

The product-page title refers to a broader “1–2 MW / 2–6 MWh” family, while its table publishes only 1.5 MWh / 750 kW and 2 MWh / 1 MW configurations. The article and quotation should use the tabled model. Any 1.2 MW or 2.6 MWh offer requires a separate manufacturer-issued data sheet.

KRL’s C&I ESS solution overview provides broader architecture context. Contractual performance should remain tied to the exact B2M6L model and project documents.

Close the 380 V and 400 V Interface Before Purchase

The factory requirement states 380 V three-phase. The B2M6L public table states 400/230 Vac. That difference affects current, transformer ratio, protection settings and the power available at the customer bus.

At 400 V and power factor 1.0, 750 kW produces approximately 1,083 A. At 380 V, the same 750 kW produces approximately 1,139 A, slightly above the published 1,130 A maximum AC current. This calculation shows why the quotation must define the connection voltage and current limit together.

The approved single-line diagram should state:

A quotation that says “380/400 V compatible” without a model-specific drawing leaves a material interface unresolved.

Prove the Transformer Black-Start Sequence

If a transformer is installed between the PCS and the 380 V production bus, the off-grid restoration sequence must account for transformer magnetizing inrush. Inverter-based sources are current-limited, and energizing a dead transformer can cause a voltage collapse or protection trip when the PCS, transformer and switching method are poorly coordinated.

The supplier should define the selected method:

Approval requires the actual transformer magnetizing curve, residual-flux assumption, PCS instantaneous current limit, protection thresholds and cable data. The FAT or SAT should energize the offered transformer from a de-energized bus under the approved worst-case sequence. KRL’s public B2M6L table does not publish a transformer black-start capability, so this function must be confirmed for the offered project configuration.

Calculate Source Impedance and Arc-Strike Voltage Dip

The transformer remains in the circuit after startup. Its percentage impedance, winding resistance and leakage reactance add to the PCS output filter, cables, switchgear and busbar impedance. A large line-to-line welding pulse can therefore create a deeper voltage dip at the 380 V production bus than a steady-state power calculation predicts.

The electrical study should provide:

Short-circuit ratio alone cannot describe a current-limited inverter bus. The final decision should combine the impedance calculation with an electromagnetic-transient or manufacturer-validated dynamic study and a witnessed voltage-dip test.

A manufacturer-approved native 380 V PCS configuration may remove the added transformer impedance. This option can be selected only when KRL provides the corresponding model number, current rating, protection settings, certification boundary and warranty. The published 400/230 Vac B2M6L configuration should not be changed through an assumed firmware setting.

Calculate Runtime from the Actual Production State

Nominal arithmetic gives a useful upper reference:

Average supported loadNominal 1.5 MWh arithmetic
300 kW5.0 hours
400 kW3.75 hours
500 kW3.0 hours
600 kW2.5 hours

These values divide nominal battery energy by average load. Available AC runtime will be lower after applying the project’s usable state-of-charge window, conversion losses, auxiliary consumption, temperature limits, reserve state of charge and capacity-aging criterion.

The purchase specification should therefore define runtime through a transparent equation:

Required nominal energy = (average supported load × required hours + auxiliary energy) ÷ approved usable-energy factor

The usable-energy factor must come from the signed technical schedule. KRL’s public page does not state usable AC energy, round-trip efficiency for this model or end-of-life retained capacity. Those values belong in the quotation and acceptance test.

Verify Arc-Welding Power Quality and Dynamic Performance

The 250 kW difference between the 750 kW PCS rating and the stated 500 kW aggregate load provides steady-state headroom. Dynamic acceptance requires separate evidence. Welding current can change quickly, and the response depends on welder topology, control settings, duty cycle and the strength of the AC bus.

The engineering review should include:

Acceptance criteria should use measurable values at the point of common coupling. Marketing descriptions such as “handles industrial surge” cannot replace the overload curve, power-quality limits and witnessed test procedure.

The witnessed test should reproduce agreed production states: one welding group, two overlapping groups, the approved maximum overlap and the controlled restart sequence. Record voltage, frequency, phase current, kW, kVA, power factor and harmonic response against timestamped acceptance limits.

Test Sub-Cycle Arc-Strike Current

RMS current and one-second trends cannot describe the first milliseconds of an arc strike. A short current peak can reach the PCS hardware-current limit before the slower supervisory controls react. The purchase specification should therefore request:

Fast hardware protection can prevent damage by turning off a power device. Continuous production requires a second result: the PCS must limit the arc-strike current, preserve the AC bus within the agreed voltage envelope and recover without an unacceptable plant-wide trip. The supplier can protect proprietary circuitry while still providing a signed protection block diagram, threshold table, response-time data and witnessed waveforms.

The acceptance test should use representative welders or a validated load emulator. Passing a steady-state 500 kW test does not prove arc-strike performance. KRL’s public product table does not state a sub-cycle current envelope or hardware-protection architecture, so the supplier must provide model-specific evidence before the system is released for production duty.

KRL B2M6L container BESS facing forward in a welding factory commissioning bay with L1 L2 L3 phase paths and arc-strike current review graphics

Select the Operating Mode Around Production Priorities

The control sequence should reflect how the welding line makes money. A practical hierarchy is:

If the factory has a diesel generator, the proposal must define its rated kVA, minimum stable load, voltage regulator behavior, frequency control, step-load capability and charging limit. KRL lists a diesel-generator port for the B2M6L, while the public page does not define compatibility with every generator or the final control sequence.

Define Diesel–BESS Dynamic Support

The generator and BESS should have a signed operating narrative for grid outages. The selected control mode must identify which source forms voltage and frequency, how active and reactive power are shared and how each source responds when a welding arc starts or stops.

The control schedule should define:

The reserved state-of-charge band matters because a full battery cannot absorb a large load rejection and a depleted battery cannot support an arc-strike increase. The EMS should keep enough two-direction power headroom for the agreed production state.

The generator-support test should switch the largest approved welding group on and off while the generator is online. Record generator kW, kvar, frequency, voltage, speed or governor response, BESS kW and kvar, state of charge and PCS current limiting. Repeat the test at the operating points agreed with the generator manufacturer.

Active filtering, virtual-synchronous-machine control and fast bidirectional generator support are separate capabilities. KRL’s public B2M6L table does not confirm these functions. Include them only when the offered PCS and EMS documents define the mode, limits and acceptance test.

KRL B2M6L container BESS and a separate diesel generator in a Nigerian welding factory microgrid test yard with dynamic support requirements

KRL’s published Nigeria industrial off-grid and diesel-hybrid solution can help frame the operating discussion. The welding-plant design still requires its own load data and single-line diagram.

Treat the 720 kW PV Input as an Available Interface

The selected B2M6L table lists up to 720 kW of PV input across six MPPT channels. The factory can purchase the BESS before installing the full PV array, provided the final architecture supports the intended phase plan.

For a PV option, the design should state:

PV capacity alone does not determine backup runtime. Battery state of charge at the moment of an outage, live solar output and the active production schedule determine the available duration.

Control Excess PV During Island Operation

At high battery state of charge, PV production can exceed the live welding and auxiliary load. The EMS and inverter controls must reduce incoming PV power before the battery, DC link or PCS reaches a protection boundary.

The control schedule should define:

The SAT should repeat a high-PV, high-state-of-charge event and then remove the agreed welding load step. Record PV power, battery power, DC-link voltage, AC voltage and control response. The public B2M6L table lists the PV input rating and MPPT limits, while it does not publish this island-mode curtailment sequence; it belongs in the project control narrative and acceptance procedure.

Specify Outdoor Protection and Site Works

The public B2M6L table lists IP65 for the battery. It does not state that every PCS compartment, connector, gland, auxiliary panel and field-installed interface carries the same rating. The contract should identify the IP rating of each delivered enclosure.

For an outdoor Nigerian industrial site, the installation package should include:

KRL lists liquid cooling, a fire-protection system and operation from −10°C to 55°C. Final thermal performance requires the project derating curve, auxiliary-power schedule and approved maintenance clearances.

The KRL testing and certification overview can support an evidence request. Buyers should obtain certificates and test reports that identify the offered model, applicable system boundary and document revision.

Qualify the Battery-Side Pulse Duty

The system-level power-to-energy ratios are approximately 0.33C at 500 kW and 0.5C at the published 750 kW rating, using 1.5 MWh as the nominal-energy base. These ratios describe average system operation. The cells can see a different waveform because the PCS DC link, switching controls, filters, parallel strings and auxiliaries shape the battery current.

The battery qualification package should identify:

Use the measured battery-side current spectrum to select the solution. Available responses can include additional parallel capacity, a cell with a verified higher-power envelope, more DC-link or pulse-buffer capability, revised PCS controls or production load sequencing. Each option requires model-specific thermal and lifetime evidence.

KRL’s public B2M6L table identifies LiFePO4 chemistry, 832 V and 1,884 Ah. It does not publish the cell model, continuous cell C-rate, pulse C-rate or ripple-current envelope. The proposed system should therefore remain described as an LFP configuration until KRL supplies the exact cell and verified pulse-duty data. A solid-state or semi-solid-state alternative should enter the proposal only with a container-scale model number, electrical ratings, safety evidence, warranty and delivery scope for this application.

Define the Five-Year Warranty in Measurable Terms

A request for a five-year battery warranty should become a signed schedule containing:

Rapid changes in welding power do not automatically prove that the cells experience identical charge-discharge micro-cycles. The PCS DC link, control bandwidth and filtering can change the battery-side waveform. Before contract award, record AC-side welding pulses and obtain the corresponding battery-current and thermal response from simulation or a witnessed test.

The warranty should explicitly accept the approved welding duty and identify the limits that will be checked in BMS and EMS records. This prevents a later dispute over pulse rate, current ripple, temperature, state of charge or event logging. The public B2M6L page does not publish a five-year model-specific warranty or a welding-duty warranty envelope. The final contract should carry the requested term and the corresponding performance conditions. KRL’s company and manufacturing profile provides supplier background; the signed warranty remains the controlling document.

Compare the Full Quote Boundary

An EXW equipment number can be compared only after every vendor answers the same scope table.

Quote packageRequired entry
Battery systemExact model, nominal and usable energy, BMS, cooling and fire equipment
Power conversionPCS model, continuous kW/kVA, overload curve and off-grid capability
AC interfaceTransformer, switchgear, ATS/STS, breakers, metering and protection relays
ControlsEMS, communications, remote monitoring, licenses and cybersecurity boundary
Site connectionCables, glands, trays, terminations, earthing and lightning protection
DocumentationData sheets, SLD, drawings, certificates, manuals and settings files
TestingFactory acceptance, site acceptance, capacity test and power-quality test
LogisticsEXW point, packing, inland transport, sea freight, insurance and import scope
Site servicesFoundation, crane, installation, commissioning and operator training
LifecycleWarranty, spares, preventive maintenance and response times

KRL’s battery packaging and global shipping page is relevant to the logistics workstream. The commercial comparison should also use a common landed-cost boundary. For cost-model structure, buyers can reference KRL’s commercial energy storage cost overview while replacing generic assumptions with project quotations.

Purchase Recommendation for the 500 kW Welding Plant

The KRL B2M6L 1.5 MWh / 750 kW configuration aligns with the stated requirement at the preliminary-selection level:

Release the purchase order after the supplier closes these approval gates:

For an engineered proposal, use KRL Power’s custom energy solution channel and include the load register, production schedule, single-line diagram and required runtime in the request.

Commercial Decision

The 1.5 MWh / 750 kW B2M6L configuration deserves detailed quotation for this 500 kW Nigerian welding plant. Its public ratings create a workable preliminary power and energy envelope. Purchase approval still requires per-phase load limits, independent fast protection, the 380 V bus-strength study, diesel–BESS dynamic controls, battery-side pulse qualification, usable-energy definition, IP scope, warranty conditions and a complete balance-of-system boundary.

Closing those items gives the buyer a comparable quotation and gives KRL a buildable project basis. The resulting proposal can protect production continuity, control future PV or generator integration and prevent scope disputes during installation.

FAQ

It provides 250 kW of three-phase nameplate headroom over the stated aggregate load. Approval also requires per-phase current, phase-pair concentration, negative-sequence capability, simultaneous demand and the PCS overload curve.

Nominal energy arithmetic gives three hours. Contractual runtime must use usable AC energy after reserve, conversion losses, auxiliaries, temperature and aging conditions.

The public table lists 400/230 Vac. The final design must define a manufacturer-approved 380 V configuration or a transformer arrangement with current limit, percentage impedance, bus-strength, voltage-dip and protection results.

kVA captures current associated with power factor. The PCS, transformer, cables and breakers must carry the resulting current, and the engineering review must also include the welding waveform.

Map every welder to its phase or phase pair, measure per-phase RMS and arc-strike current, calculate the worst simultaneous combination and verify the PCS per-leg, negative-sequence, zero-sequence and neutral limits that apply to the offered topology.

It provides a published maximum AC-current reference. Approval still requires the arc-strike peak, per-phase pulse duration, independent hardware-protection function, current-limiter response and simultaneous-welder test.

The public table states IP65 for the battery. Obtain component-level ratings for the PCS, connectors, auxiliary panels and completed field interfaces.

The public product page does not state a model-specific five-year warranty. Put the requested term, capacity obligation, accepted welding-duty profile, current-ripple limits, conditions and remedy into the signed warranty schedule.

The 1.5 MWh configuration lists 720 kW maximum PV power, six MPPT channels, a 250–850 Vdc MPPT range and 200 A per channel. The final design must also define island-mode curtailment when the battery is full and PV exceeds the live load.

The public table lists a diesel-generator port. The project must approve generator kVA, governor and AVR settings, BESS operating mode, two-direction power reserve, load-step response, charging limit, synchronization and transition logic.

Verify model identity, per-phase unbalanced loading, fast hardware protection, communications, thermal controls, alarms, switching logic, arc-strike current limiting, battery-side pulse response and the approved transformer-energization sequence before shipment.

Test the installed sources, phase imbalance, bus voltage dip, transformer black start, representative welding arcs, diesel–BESS load support, maximum group overlap, emergency isolation, runtime method and PV load rejection where those sources are installed.

Select the cell and pulse-buffer solution from the measured battery-side current spectrum, RMS ripple, peak duration, temperature rise and lifetime target. KRL must provide the exact cell model and verified operating envelope for the offered container.

The preliminary option is the published KRL B2M6L 1.5 MWh and 750 kW configuration for a stated 500 kW aggregate load. Final selection depends on phase loading, welding transients, the 380 V interface and project acceptance evidence.

Include it whenever a diesel generator will operate with the BESS during grid outages. The design must define voltage and frequency control, power sharing, charging and discharging reserve, load-step response and source transitions.

The KRL B2M6L product page publishes the 1.5 MWh and 750 kW table values used for preliminary review. Project-specific functions, cell pulse limits, warranty and the 380 V connection require signed technical documents.

Envoyez votre demande dès aujourd'hui

Obtenez votre solution énergétique sur mesure en 24 heures

Ne payez plus les marges des marques. Collaborez directement avec une usine qui existe depuis 20 ans.

KRL Power — Le moteur des projets énergétiques mondiaux

Reconnu dans le monde entier :

UL, CE, CEI, UN 38.3

Mannequins sexy :

B65 · B100 · B241 · B26LL · B61LL · B522L · B2M6L

Applications :

Usines · Parcs solaires · Exploitations minières · Îles · Centres de données

Parlez-nous de votre projet : nous concevrons le système sur mesure pour vous.