KRL | Custom Lithium Battery & Energy Storage(BESS)Manufacturer

Download Technical Specs PDF

Contents

Bangladesh Textile Mill Backup Power: A 4 MWh–8 MWh Solar-Storage-Generator Microgrid Design

Engineering review by Liu, KRL Power R&D Director—20 years of C&I energy-storage engineering experience, formerly in Huawei R&D.

A spinning mill in Bangladesh needs a battery energy storage system to keep 900 kW of critical production load operating for four hours after a utility outage. The factory’s maximum demand is 1,553 kW. It already has a 200 kW Huawei AC-coupled PV system, plans to add 700 kW of solar, receives utility power at 33 kV, and has a 1,500 kVA gas generator plus a 50 kVA diesel generator.

This is an excellent application for a solar-storage-generator microgrid, but the solution cannot be selected from nominal MWh alone. KRL must distinguish battery nameplate energy from usable AC energy, isolate the critical process bus, confirm how the existing PV inverter behaves during an outage, and coordinate the BESS with the generators, transformer, switchgear and protection system.

KRL Power’s 1 MW / 2 MWh all-in-one platform is a strong building block for this project. Battery, PCS, MPPT, BMS and EMS are integrated in one liquid-cooled 20-foot unit, so the new DC-coupled PV array does not require a separate PV inverter.

bangladesh-textile-mill-krl-4mwh-bess-installation

Customer Requirements and Engineering Meaning

Design inputCustomer dataEngineering meaning
Maximum factory load1,553 kWBasis for the full-factory option
Critical outage load900 kWRequires a dedicated critical-load bus
Backup duration4 hoursRequires 3.60 MWh net AC energy
Existing PV200 kW Huawei, AC-coupledIsland compatibility must be verified
Planned PV700 kWCan use KRL’s integrated MPPT inputs
Utility supply33 kV, 50 HzRequires transformer and MV/LV coordination
Generators1,500 kVA gas + 50 kVA dieselGas unit is the relevant production backup
InstallationIndoorRequires structural, cooling and fire review

The matched KRL product data supplied for this project is:

KRL product parameterApproved project value
Battery energy2 MWh per unit
Bidirectional PCS1 MW per unit
Integrated MPPT960 kW, eight inputs
Operating modeGrid-connected, off-grid and seamless switching
IntegrationBMS, PCS and EMS
Mechanical designLiquid-cooled 20-foot container; battery enclosure IP65
CommunicationsRS485, WiFi or 4G

This article describes an engineering proposal, not a completed installation. Final runtime, quantities and ROI remain conditional on the load profile, site single-line diagram, transformer data, PV module datasheet and indoor-room conditions.

Energy Verification: Why 4 MWh Is a Hybrid Backup Option

The critical load requires:

900 kW × 4 h = 3,600 kWh = 3.60 MWh AC

That is energy delivered at the load bus. Nominal battery energy must still cover reserve SOC, PCS and cable losses, cooling and control auxiliaries, temperature effects and future capacity fade.

For a preliminary screening calculation, assume a 90% operating SOC window, 94% discharge-chain efficiency and a 3% auxiliary reserve. These are planning factors, not product warranty values:

4.00 MWh × 0.90 × 0.94 × 0.97 ≈ 3.28 MWh AC

At a constant 900 kW load, 3.28 MWh provides approximately 3.65 hours. Therefore, two 2 MWh units should not be sold as an unconditional battery-only four-hour guarantee. They form a credible economic hybrid solution when the 700 kW PV array, the 1,500 kVA gas generator or controlled load reduction supplies the remaining energy and operating reserve.

If the customer requires four hours with no PV and no generator support, the contract must state whether the guarantee applies at beginning or end of battery life. A 6 MWh nominal configuration should be evaluated for a firm end-of-life 900 kW duty, subject to the actual warranted usable energy and retention curve.

krl-4mwh-8mwh-backup-energy-validation

Option 1: 2 MW / 4 MWh for the 900 kW Critical Load

The economic solution uses two KRL 1 MW / 2 MWh all-in-one units in parallel. The combined system provides 2 MW PCS power, 4 MWh nominal energy and 1.92 MW integrated MPPT capacity.

An engineered low-voltage AC combiner cabinet is required. Each PCS output needs its own breaker, metering, isolation and coordinated protection before connection to the common microgrid bus. This is an AC output combiner, not an external PV inverter or PV combiner.

The 2 MW PCS rating provides substantial headroom above the 900 kW steady load, but motor-start performance must still be verified. KRL needs the largest motor rating, VFD or soft-starter data, acceleration time, transformer inrush, starting sequence and PCS overload curve.

In normal operation, the EMS maintains the required backup SOC while using available capacity for peak shaving. After a grid failure, the islanding device separates the critical bus and the PCS supports the islanded network. New PV serves the load first and charges the battery with surplus energy. At the generator-start SOC threshold, the EMS calls the 1,500 kVA gas generator and applies loading and reverse-power limits. The 50 kVA diesel generator remains an auxiliary source and cannot carry the production bus. This configuration uses the existing gas generator as resilience margin instead of oversizing the battery for an occasional worst-case event.

Option 2: 4 MW / 8 MWh for Full-Factory Backup

Four KRL units provide 4 MW PCS power and 8 MWh nominal energy. The theoretical energy required by the 1,553 kW maximum factory load is:

1,553 kW × 4 h = 6.212 MWh AC

Using the same screening factors, 8 MWh provides approximately 6.56 MWh AC at beginning of life, or about 4.23 hours at 1,553 kW. At 80% retained capacity, this falls to about 5.25 MWh or 3.38 hours. A firm end-of-life target therefore needs PV or generator support, controlled load shedding, different warranted performance, or evaluation of approximately 10 MWh nominal capacity.

The preliminary 3.5–4.5-year payback must not be published as a guarantee. ROI should be calculated from tariffs, demand charges, fuel, outage hours, production losses, PV yield, CAPEX and operating strategy.

PV Integration Without an External PV Inverter

The existing 200 kW Huawei PV system remains AC-coupled. It can operate inside a battery-formed island only if its model, firmware, anti-islanding settings, voltage/frequency response, curtailment and reconnection logic are compatible with the KRL controller. Until verified, it should not be counted as firm outage generation.

The new 700 kW array connects directly to the KRL units’ integrated MPPT inputs. Although it is below one unit’s 960 kW MPPT rating, splitting strings across two units improves power sharing. Final design still requires module Voc, Vmp, Isc, temperature coefficients, MPPT limits and cable data. Variable PV can extend runtime but should not support a contractual autonomy guarantee without a conservative energy model.

bangladesh-textile-mill-solar-storage-generator-topology

400 V or 33 kV: Closing the Interconnection Boundary

At 400 V and unity power factor, 2 MW is approximately 2,887 A and 4 MW is approximately 5,774 A. A dedicated 400 V critical bus can simplify backup, but switchgear, busbars, cables and fault duty must support these currents.

For a 33 kV connection, the low-voltage PCS must feed a correctly rated step-up transformer and MV switchgear; it must never connect directly to 33 kV. The 4 MW option may require split LV sections or unit transformers. Seamless switching remains a system-level commissioning result determined by the transfer device, protection, transformer, controls, motors and PV compatibility.

Indoor Installation Review

IP65 does not by itself approve a 20-foot BESS for indoor use. The review must confirm delivery access, floor loading, anchoring, maintenance and emergency clearances, liquid-cooling heat rejection, fire detection and suppression, gas/deflagration risk, ventilation, earthing, fire stopping, emergency stop and isolation. Final design must follow Bangladesh requirements without claiming undocumented certification.

indoor-2mwh-bess-installation-engineering-checks

Data Required Before the Final Proposal

Engineering Conclusion

Two KRL 1 MW / 2 MWh units, an AC combiner, 700 kW of new DC-coupled PV, the existing 200 kW AC PV and the 1,500 kVA gas generator form a technically credible hybrid microgrid for the 900 kW critical load. The 4 MWh option should be presented as an economic hybrid-backup solution rather than an unconditional battery-only four-hour guarantee.

Four KRL units provide a credible 8 MWh beginning-of-life option for the 1,553 kW maximum factory load. Final approval depends on closing the 400 V versus 33 kV connection, verifying the indoor site, testing existing PV compatibility and defining whether runtime applies at beginning or end of battery life.

Review the KRL B2M6L 1–2 MW / 2–6 MWh product family, the KRL commercial and industrial energy storage portfolio, and contact KRL Power with the load profile, SLD, transformer data, PV datasheet and room drawings.

FAQ

No. It may support controls or auxiliaries. The 1,500 kVA gas generator is the relevant production source, subject to real-power rating, derating and EMS coordination.
The 400 V option can simplify critical-load backup but creates high current. A 33 kV connection requires a step-up transformer and MV switchgear. The final choice depends on the site SLD, transformer arrangement, fault level and cable route.
No. Indoor approval still depends on structure, access, maintenance spacing, heat rejection, fire safety, emergency egress and local authority requirements.
Not without the customer’s tariff, demand charges, outage costs, fuel prices, PV yield, CAPEX and operating schedule. KRL should provide an auditable ROI model based on actual bills and outage records.
Commissioning should verify protection coordination, grid-loss detection, island formation, load steps, motor starting, PV curtailment, generator control, reverse-power protection, SOC reserve, emergency stop, communications and grid restoration.

Get Your Custom Energy Solution in 24 Hours

Stop Paying for Brand Markups. Partner Direct with a 20-Year Source Factory.

KRL Power — Source Factory Behind Global Energy Projects

Trusted Worldwide:

UL, CE, IEC, UN38.3

Hot Models:

B65 · B100 · B241 · B26LL · B61LL · B522L · B2M6L

Applications:

Factories · Solar Farms · Mining · Islands · Data Centers

Tell us your project — we'll design the system for you.