...

KRL | Custom Lithium Battery & Energy Storage(BESS)Manufacturer

Download Technical Specs PDF

Contents

Bangladesh Textile Factory Hybrid Microgrid: Can a 964 kWh Battery Support 300 kW for 3 Hours?

A Bangladesh textile factory is evaluating lithium battery storage for a 300 kW critical load, three hours of backup and direct solar charging. The site has an 11 kV/415 V, 630 kVA transformer and a diesel generator. A current quotation is based on four 241 kWh units, or 964 kWh nameplate.

The decisive question is whether the battery alone must carry 300 kW for three hours, or whether solar and the generator may contribute. That boundary changes capacity, controls, acceptance testing and price.

bangladesh-textile-factory-krl-hybrid-microgrid-1

Quick answer

The correct commercial offer therefore depends on one written answer: battery-only autonomy, or hybrid-system autonomy?

Project facts and design boundaries

ItemCustomer informationEngineering implication
FacilityTextile factory, about 42,000 sq ftRoof area is not the same as usable PV area; a structural and shading survey is required
Critical load300 kWConfirm average, peak, step load, motor starts and power factor from measured data
Backup duration3 actual operating hoursAcceptance criteria must define whether PV and diesel may contribute
Existing transformer630 kVA, 11 kV/415 VVerify spare kVA, impedance, vector group, LV bus rating and fault level
Existing backupDiesel generatorObtain nameplate, minimum loading, controller, breaker and synchronization data
Battery technologyLithium requiredSpecify safety, usable-energy warranty, thermal management and commissioning tests
Solar requirementDirect solar charging plus complete PV solutionRoute PV strings to the KRL system’s integrated MPPT; no separate PV inverter is required for this DC-coupled concept

The customer should remain anonymous publicly without written permission. These are pre-design calculations, not a final EPC drawing or warranty.

Start with delivered energy, not catalogue capacity

The requested service is 300 kW for three hours:

Required AC energy = 300 kW × 3 h = 900 kWh

Nameplate capacity cannot be compared directly with the 900 kWh duty. Account for the permitted state-of-charge window, conversion losses and auxiliaries.

For an initial screen:

Deliverable AC energy = nameplate kWh × 0.90 × 0.94 × 0.97

ConfigurationNameplate energyScreened AC energyRuntime at 300 kW
Four 241 kWh units964 kWh≈791 kWh≈2.64 h
KRL standard energy block1,000 kWh≈821 kWh≈2.74 h
Preliminary battery-only minimum≈1,097 kWh900 kWh3.00 h
bangladesh-300kw-3hour-energy-validation-2

These factors are planning assumptions, not guaranteed values. Final sizing must use warranted usable energy, PCS efficiency, site temperature, auxiliaries, degradation and the end-of-life guarantee.

The recommended solution is hybrid three-hour resilience: use the KRL 500 kW/1 MWh system with direct solar and automatic generator support. If the customer later changes the acceptance criterion to battery-only autonomy, the energy capacity must be recalculated and increased.

Check power separately from energy

The 500 kW PCS exceeds the stated 300 kW continuous load, but motor starting and process transients still require verification.

List every protected motor, starting method, starting current, allowable voltage dip and restart sequence. A staged restart can reduce instantaneous power.

At 415 V, the 630 kVA transformer is about 876 A full-load. A 300 kW load at 0.95 power factor is roughly 439 A; a 500 kW PCS at unity power factor could approach 696 A at full output. The EMS must limit charging against live factory demand. “Reserved capacity” does not replace interval data and protection calculations.

Recommended KRL hybrid architecture

The concept uses one controlled 415 V microgrid bus:

bangladesh-textile-factory-hybrid-topology-3

The KRL platform combines a 1 MWh lithium battery, 500 kW PCS, 480 kW total MPPT with four routes, BMS/PCS/EMS controls, liquid cooling, an IP65 battery cabinet and RS485/Wi-Fi/4G communications in a 20-foot container. It supports on-grid and off-grid operation with seamless switching. Final selection is subject to the approved single-line diagram and site study.

How the system should operate

Normal grid operation. Solar serves loads and charges the battery within the transformer limit. The EMS retains the agreed resilience reserve.

Daylight outage. The PCS supports the critical bus while PV continues through the integrated MPPT. Surplus PV charges the battery; the battery covers a PV shortfall.

Low solar or low state of charge. The EMS starts the generator before the reserve is exhausted, while respecting its stable loading range.

Grid return. Controls verify electrical conditions, transfer or resynchronize under the approved scheme, then ramp charging without creating a new peak.

bangladesh-textile-factory-operating-strategy-4

Solar scope for a 42,000 sq ft factory

The gross building area is about 3,902 m², but usable PV area is reduced by structure, shading, drainage, skylights, fire setbacks and access lanes.

KRL can screen a direct-DC PV array in the 350–480 kWp range. Final size depends on the roof survey, module/string design, temperature and the 480 kW MPPT envelope. Generation, recharge time and any grid export require site data and the current Bangladesh utility/SREDA approval path.

Business case: measure the four value streams

A proposal should quantify rather than assume:

Use 12 months of bills, interval load data, outage history, generator fuel/run hours, diesel price, production losses, roof results and the customer’s financial horizon.

Safety, approvals and acceptance testing

Confirm requirements with the local authority, utility, insurer and EPC. Relevant international references include IEC 62619, IEC 63056 and IEC 62933-5-2.

Before handover, test protection, emergency stop, communications-failure behaviour, transitions, generator control, PV curtailment, load shedding and autonomy. Record initial state of charge, load, allowed source contribution, ambient conditions and pass/fail boundary.

RFQ checklist before a firm quotation

Send the following information to KRL:

Conclusion

The project should not be sold as “964 kWh equals three hours.” Its real requirement is 900 kWh delivered to a 300 kW AC load, and the initial energy screen shows a meaningful gap after normal operating limits and losses. The KRL 500 kW / 1 MWh all-in-one platform is a credible centrepiece for the requested solar–grid–diesel microgrid, especially when PV or the generator may support the outage window. If the customer requires three hours from the battery alone, KRL should size a larger energy block against a written usable-energy and end-of-life guarantee.

Review KRL’s commercial and industrial energy storage systems, explore C&I ESS solutions, or send the project data to KRL for a validated single-line concept, capacity calculation and commercial proposal.

Frequently asked questions

Sources

Send Your Inquiry Today

Get Your Custom Energy Solution in 24 Hours

Stop Paying for Brand Markups. Partner Direct with a 20-Year Source Factory.

KRL Power — Source Factory Behind Global Energy Projects

Trusted Worldwide:

UL, CE, IEC, UN38.3

Hot Models:

B65 · B100 · B241 · B26LL · B61LL · B522L · B2M6L

Applications:

Factories · Solar Farms · Mining · Islands · Data Centers

Tell us your project — we'll design the system for you.

Seraphinite AcceleratorOptimized by Seraphinite Accelerator
Turns on site high speed to be attractive for people and search engines.